September 20, 2021: Crews testing transmission line technology in Labrador and on the Island September 20 to October 4.
September 20th, 2021 by Laura Fifield
As part of commissioning of the Labrador Island Link (LIL), live testing of the Electrode Line Fault Locator technology is planned for the next several days. This technology will help teams locate issues along the electrode line in Labrador from Muskrat Fall to Forteau, and on the Island from Dowden’s Point to Soldiers Pond. It […]
Investigation of water surface film downstream from Muskrat Falls Site
September 10th, 2021 by Laura Fifield
September 10, 2021 Update During a helicopter survey this morning, areas with a surface water film were observed downstream of the Muskrat Falls site. We are investigating. We have mobilized our emergency response teams. Members of the Lower Churchill Project St. John’s EOC team are monitoring the situation in conjunction with the MF team at […]
June Benefits Report
August 16th, 2021 by Laura Fifield
June 2021 Monthly Benefits Report is available here
May Benefits Report
July 15th, 2021 by Laura Fifield
May 2021 Monthly Benefits Report is available here
Safety Advisory
July 6th, 2020 by Karen ONeill
New: Safety advisories for maintenance work on LIL
April Benefits Report
July 6th, 2020 by Karen ONeill
April Benefits Report is available here
June 2020 – COVID-19 measures in place at Muskrat Falls site
July 6th, 2020 by Karen ONeill
Safety measures In late May 2020, we resumed construction and commissioning of the Muskrat Falls Project. As we work through the process to safely resume work, we are adhering to the new protocols and guidelines that have been developed for the protection of workers from COVID-19 in the construction industry. The health and well being […]
April 2, 2020: Measures in place at the Muskrat Falls site to keep people safe
April 2nd, 2020 by admin
We are actively monitoring and addressing the evolving COVID-19 pandemic and the potential risks to our people, our communities and site operations. On March 17, we announced the suspension of construction activities at the Muskrat Falls site in Labrador and then placed the site into care and maintenance mode with an essential workforce. This team […]
COVID-19: An update on the Muskrat Falls Project (March 27) is available here
March 27th, 2020 by admin
COVID-19: An update on the Muskrat Falls Project (March 27) is available here
COVID-19 Message from Nalcor’s CEO
March 26th, 2020 by admin
March 26, 2020: During this uncertain and unprecedented time, Nalcor Energy and its lines of business have taken measures to ensure the safety and well being of our employees, while positioning ourselves to continue to serve the people of Newfoundland and Labrador. We understand that the people of our province rely on us, and I want […]